TECNOADMIN CONSULTING
Project Track Record & Capability Report · 1992 – 2026
Martin Obando Loor
Electrical Engineer (ESPOL) · MBA (ESPAE) · PhD candidate, Universidad de Querétaro (Mexico), 2026–2029
AACE International — Past President, Ecuador Section · Vice-President, Peru Section
PMI member #1373492 · CRIEEL reg. 03-G-902
Guayaquil, Ecuador · Issued August 2026

Professional profile

Martin Obando has 34 years of experience in the planning, control and management of civil and electromechanical projects, of which the last 19 have been dedicated almost entirely to mining and metallurgical developments. He has held roles as project manager, construction manager, project control manager and lead planner on programmes ranging from USD 5 million to USD 5 billion, across ten countries.

His practice covers the full control cycle: baseline development and rolling-wave planning, critical-path and earned-value control, contractor schedule acceptance, probabilistic scheduling and quantitative risk analysis (P50/P80), 4D construction simulation, and the set-up and audit of project control systems and PMOs. He also practises forensic schedule and delay analysis in support of contract claims — a discipline he entered in 1992 with Construction Interface Inc. and continues today alongside legal counsel — most recently in an arbitration over a hydroelectric plant built in Ecuador, decided in the client's favour in July 2025, and in the ongoing rebuttal of a contractor's claim at Nexa's Cerro Lindo mine.

A distinct and growing part of the practice is independent schedule assurance: being engaged by owners to review, test and comment on programmes prepared by others — the audit of the Nueva Centinela schedules for Antofagasta Minerals, and the role of schedule reviewer on the Independent Project Reviews (IPR) of the Vicuña and Escondida project portfolios for BHP and of the Resolution Copper project.

A second area of expertise is artificial intelligence: Martin specialises in AI-assisted software development, and it is that capability which allowed a consulting practice — not a software house — to design, build and deploy a full product line in six months, described under Proprietary digital products below.

Portfolio at a glance

Summary
Span of practice1992 – 2026 · 34 years
Projects supported70+ projects, studies and due diligences
CountriesEcuador, Peru, Chile, Argentina, Colombia, Brazil, Uruguay, El Salvador, Canada, United States
SectorsMining and metallurgy · Hydroelectric and power · Oil and gas · Airports and ports · Water and sanitation · Urban infrastructure · Buildings and hospitality · Defence facilities
Largest programmesVicuña capital portfolio, BHP (USD 17 BB — IPR) ·Nueva Centinela, AMSA (USD 5 BB) ·Las Bambas Stage II (USD 2.8 BB) · Coca Codo Sinclair (USD 2,500 MM) · Gran Colombia Gold–Silver (USD 1.2 BB) · Fosfatos del Pacífico (USD 900 MM) · Milpo master feasibility (USD 700 MM) · Fruta del Norte (USD 692 MM)
Owners and majors servedBHP · Antofagasta Minerals · Nexa Resources · Barrick · Antamina · Lundin Gold · Southern Peru Copper (SPCC) · Volcan · Milpo · Minera Las Bambas · Antapaccay · Aceros Arequipa · Fosfatos del Pacífico · Gmining · BP · EnCana · Odebrecht · US Army Corps of Engineers
Core servicesSchedule development and control · Independent Project Review (IPR) and schedule audit · Project control set-up · Probabilistic scheduling and risk (P50/P80) · 4D construction simulation · Claims and forensic delay analysis · PMO implementation
ToolsetPrimavera P6 and P3 · Primavera Risk Analysis · Contract Management / Expedition · Microsoft Project · Navisworks and Synchro 4D · Opus · SAP · QuickBooks

Part A · Current engagements (2024 – 2026)

Work carried out since the last revision of the curriculum vitae.

PeriodProject / ClientCountryCapital valueRole and contribution
Jul 2026 – presentCerro Lindo Extension of Time & Acceleration Claim — Contract Coupa 1150 · Nexa ResourcesPeruUSD 6.31 MM claimedSchedule and delay expert on the owner's side, preparing the rejoinder to the contractor's extension of time and acceleration claim. Applied windows delay analysis to the contemporaneous programme updates — dividing the works into analysis windows to establish what actually drove the critical path in each period — and tested the asserted entitlement against the contract and the contemporaneous project record. Engaged directly by Nexa, ongoing since July 2026.
Mar – Jul 2026Resolution Copper project — Independent Project Review (IPR) · Rio Tinto / BHP, through BedRock ServicesUSAUSD 14 BBSchedule reviewer on the Independent Project Review of the Resolution Copper project: reviewed and formally commented the programmes prepared by the project teams — schedule structure and logic, critical path, duration basis and interface consistency — with observations returned to the owner as part of the IPR governance process.
February 2026Vicuña project portfolio — Independent Project Review (IPR) · BHP, through BedRock ServicesArgentina / ChileUSD 17 BBSchedule reviewer on BHP's Independent Project Review of the Vicuña portfolio, a capital portfolio of USD 17 billion. Assessed programme structure, logic, critical path, duration basis and interface consistency across the constituent projects, and issued formal review comments to the owner as part of the IPR governance process.
December 2025Escondida project portfolio — Independent Project Review (IPR) · BHP, through BedRock ServicesChileUSD 10 BBSame IPR role at the world's largest copper operation: five Escondida programmes were reviewed and formally commented — schedule logic and structure, critical path, duration basis and interface consistency across the portfolio — with observations returned to the owner's project teams.
Nov 2025 – presentEl Porvenir and Atacocha mines (Pasco complex) – capital works programme · Nexa Resources (consultant to the owner; contractor: Construplan)PeruUSD 80 MMOwner's planning and project control consultant on a multi-package programme across both operations: LB2 Pumping System, Tailings Storage Facility (Relavera) Phase 2, and relocation of the 60 kV transmission line. Produced the works baseline, critical path, duration basis, S-curve, resource histogram and commodity curves (excavation, fill, 10/28 MPa concrete, reinforcing steel, CS tailings pipeline, HDPE wash-water pipeline, cabling), plus the WBS and the Nexa–Construplan free-issue supply interface, and reviews the contractor's programme on the owner's behalf.
2026 – presentIntegrated Project Control Panel · Nexa Resources (Pasco complex)Perun/a (services)Designed and deployed a web-based integrated control panel consolidating schedule, progress and document-control status (CR/RS/TR series) into a single management view, replacing manual report assembly. Built on Tecnoadmin's own reporting platform (see Proprietary Digital Products).
Mar 2025 – Apr 2025Nueva Centinela project – schedule audit · Antofagasta Minerals (AMSA), through BedRock ServicesChileUSD 5 BBIndependent audit of the project schedules on one of the largest copper developments currently in execution. Reviewed the programme across the study work breakdown — legal framework, land tenure and permitting; mineral processing; and external affairs and communities — testing logic, critical path, duration basis and interface consistency between work streams, and reported findings and corrective recommendations to the owner.
Sep 2024 – Jul 2025International arbitration – Sabanilla hydroelectric plant · Estudio Jurídico Pino ElizaldeEcuador (deposition heard in Chile)USD 2 MM in disputeSchedule and delay expert supporting counsel in an arbitration arising from the construction of the Sabanilla hydroelectric plant in Ecuador. Reconstructed the as-built programme from the contemporaneous record, quantified delay and productivity loss, and prepared the technical exhibits relied on by counsel. The deposition was heard in Chile in July 2025 and the case was decided in favour of the firm's client.
Apr 2024 – presentEl Domo (Curipamba) polymetallic project · BedRock Services, CanadaEcuadorUSD 300 MMProject Scheduling and Project Control Services. Returned to Ecuador specifically for El Domo, a project supported since 2023, carrying forward the execution schedule and controls framework built at feasibility stage into the construction phase.

Part B · Mining, EPCM and consulting (2007 – 2024)

PeriodProject / ClientCountryCapital valueRole and contribution
Jan 2024 – Mar 2024Escuelas Bicentenario public-investment programme · MACE PerúPeru (Lima)≈ USD 1.6 BBLead Planner. Led the planning team in Lima and audited the processes in use for project control and monitoring, issuing recommendations to align them with programme requirements. The programme covers 75 schools across nine regions and 21 districts of Metropolitan Lima, with a published State investment of S/ 5,949 million (approximately USD 1.6 billion).
Jun 2023 – Dec 2023Chinchero International Airport, Cusco · Hyundai–HS / Consorcio NatividadPeruUSD 450 MMBuilt the comprehensive project plan for this national tourism-infrastructure programme, integrating engineering, procurement and construction into a single controllable baseline.
Feb 2023 – May 2023El Domo project – feasibility stage · DRA Global, CanadaEcuadorUSD 300 MMDeveloped the feasibility-stage plan and the engineering, procurement and construction schedule for the execution phase, and simulated the construction sequence in Navisworks 4D from early works through plant erection.
Nov 2022 – Jan 2023Project control procedures for a mining client · Metacontrol PerúPerun/a (services)Wrote the client's project control procedures covering sustainability project plans from conception to execution: planning, change control and progress tracking.
Nov 2021 – Oct 2022Multi-project portfolio (Loma Larga, La Plata, Brazil and Central America) · Gmining ServicesEcuador / Brazil / Central AmericaNot disclosedPlanning Coordinator. Migrated the portfolio from Microsoft Project to Primavera P6 and planned several concurrent projects, standardising the planning basis across regions.
Feb 2021 – Nov 2021Las Bambas Stage II expansion study · Ausenco, for Minera Las BambasPeruUSD 2.8 BBExternal consultant for the whole-programme study schedule: control of all engineering contractors' progress; risk analysis covering environmental, social and permitting exposure; and probabilistic scheduling to derive P50 and P80 programme durations.
May 2020 – Jan 2021Fortich Hotel and Lilax Hotel · CrisbecorpEcuadorUSD 50 MM (Fortich)Post-pandemic construction monitoring services for the Fortich Hotel, extended the same year to monitoring of the structural (grey) works of the Lilax Hotel.
Jun 2017 – Oct 2019Fruta del Norte (FDN) gold mine · Lundin GoldEcuadorUSD 692 MMSenior Planner Coordinator in a five-planner team on a 325 koz/y gold operation. Ran rolling-wave planning, controlled subcontractor schedules, updated engineering, procurement and construction monthly, drove deviation-mitigation actions with area managers, and produced the stakeholder reporting baseline.
Jun 2016 – Mar 2017La Libertad refinery shutdown · OmaconsaEcuadorUSD 8 MMPlanner and Engineering Manager, acting as project manager for the shutdown contract in an oil and gas refinery. Owned scheduling, client interface, cost control, procurement and delivery; the contract closed in line with the client's strategy.
Jan 2012 – Mar 2016Hatch Asociados S.A. – Lima office · Project Control LeadPeru (with Chile, Brazil, Canada, USA offices)See portfolio belowLed project controls across a multi-country studies and EPCM portfolio, managing teams distributed across Hatch offices, client interface, estimating, CAPEX and OPEX. Sub-portfolio detailed in the following table.
Jul 2010 – Dec 2011Project Management Office implementation programme · Verano, BrazilEcuador / Colombia / Peru / Uruguayn/a (services)Senior consultant implementing PMOs on PMI methodology with Primavera P6 and Contract Management for Interagua (Ecuador), BP and Petrominerales (Colombia), Corpesa and JJC (Peru) and CSI (Uruguay). Trained client teams and delivered portfolio-level scheduling procedures for critical path, cost, man-hour curves and reporting.
Dec 2009 – Jun 2010Coca Codo Sinclair hydroelectric project, 1,500 MWEcuadorUSD 2,500 MMChief of Project Planning and Control. Short but high-leverage assignment: developed solutions to release early activities for the start of construction, including the pipeline diversions at the water intake to the tunnel.
Jan 2008 – Nov 2009Cajamarquilla zinc refinery expansion 160K/320K, leaching process · Amec Perú, for Votorantim MetaisPeruUSD 400 MMScheduler Lead for the leaching area: full scope scheduling, critical path, and control of subcontractors and the main contractor. Completed the master plan, aligned subcontractor schedules to project targets, and delivered the scope on time and on budget.
Jul 2007 – Oct 2007Cajamarquilla 160K zinc refinery expansion – plant shutdown · SSK PerúPeruUSD 11 MM (contract)Chief of planning and control for a four-month shutdown peaking at 1,500 workers. The move from infrastructure into mining, and the first assignment leading a multinational workforce.

Hatch Asociados S.A. — project portfolio, Lima office (2012 – 2016)

RoleProject / ClientCountryCapital value
Project ManagerTingo hydroelectric plant – feasibility study · VolcanPeruUSD 45 MM
Project ManagerAlpamarca – EPCM · VolcanPeruUSD 160 MM
Project ManagerTin plant tailings re-treatment – feasibilityPeruUSD 200 MM
Project Manager / Project Control ManagerChancay port terminal – basic engineering · Terminales Portuarios ChancayPeruUSD 480 MM
Project Control ManagerPhosphate beneficiation plant – feasibility · Fosfatos del PacíficoPeruUSD 900 MM
Project Control ManagerTailings pond independent review support · AntaminaPeruUSD 50 MM
Project Control ManagerNorth Lakes water treatment plant – feasibility · BarrickPeruUSD 400 MM
Project Control ManagerAntapaccay 82 ktpd plant extension study · AntapaccayPeruUSD 90 MM
Project Control ManagerMaster feasibility study · MilpoPeruUSD 700 MM
Project Control ManagerCup kilns and related facilities – basic and detail engineering · SPCCPeruUSD 100 MM
Project Control ManagerContinuous casting modernisation – basic engineering · Aceros ArequipaPeruUSD 60 MM
Project Control ManagerSecond stage sulphides – definitive feasibility study · Río Alto MiningPeruUSD 130 MM
Project Control ManagerGran Colombia Gold–Silver · MedoroColombiaUSD 1.2 BB
Project Control ManagerProject JESSICA – crushing plant expansion, EPCM · ARASIPeruUSD 60 MM
Expert consultantDue diligence – La Virgen to Caripa transmission linePerun/a
Expert consultantDue diligence – Marañón hydroelectric plantPerun/a
Expert consultantDue diligence – San Gabán hydroelectric plantPerun/a

Part C · Infrastructure, industry and buildings (1992 – 2007)

PeriodProject / ClientCountryCapital valueRole and contribution
Nov 2004 – Jun 2007José Joaquín de Olmedo International Airport – fuel farm and aircraft apron · TAGSA / EKRONEcuadorUSD 100 MMProject Manager for the civil, mechanical and electrical works of the fuel farm and Construction Manager for the aircraft platform, with responsibility for planning, project control, quality control and quality assurance.
2005 – 2007Terminal Terrestre de Guayaquil · Inmomariuxi C.A.EcuadorUSD 30 MMInitial planning and monthly updates for the civil, mechanical and electrical installations.
2004New 20" submarine pipeline, RLL · Petroindustrial / OXXO S.A.EcuadorUSD 25 MMCost and project control using Primavera P3 and Expedition, including payment requisition management.
2002 – 2003Simón Bolívar Airport · Inmomariuxi C.A.EcuadorUSD 5 MMInitial planning and monthly updates, civil and electromechanical scheduling.
Aug 2002CENTAM FOL, Comalapa Air Base · ABB SUSA Inc. for US Army Corps of EngineersEl SalvadorUSD 15 MMInitial planning for a forward operating location built under US Army Corps of Engineers contract.
2002Machala Power project · Washington Group InternationalEcuadorUSD 350 MMInitial planning and monthly updates, civil and electromechanical scheduling.
2001 – 2002FOL support facilities, Manta · ABB SUSA for US Army Corps of Engineers (Mobile District)EcuadorUSD 15 MMInitial planning and monthly updates of time and cost.
2001Machala Power – civil construction · Consorcio Santos CMIEcuadorUSD 6 MMInitial planning, monthly updates and cost control.
2001FOB Phase 2, Puerto Maldonado · CEGAZ Contratistas Generales for US Army Corps of EngineersPeruUSD 7 MMInitial planning for a forward operating base.
1999 – 2002Malecón 2000 urban regeneration · GuayaquilEcuadorUSD 120 MMInitial planning and cost control on Primavera P3 and Expedition, running budget, commitment, actual cost and variance reporting on the city's flagship waterfront project.
1999Hotel Sheraton Four Points · Inmomariuxi C.A.EcuadorUSD 10 MMProject control on Primavera P3 and Expedition: budget, commitment, actual cost and variance.
1999New Hanover Medical Center, Wilmington NC · Construction Interface Inc.USAUSD 50 MMDeveloped construction processes for cost control using Expedition, acting as project consultant on a US healthcare build.
1999EPA project, Raleigh NC · Construction Interface Inc.USADeveloped administrative and cost-control construction processes using Expedition.
1998Las Cameras project – completion analysis · Rodolfo Rendón (Diplan)EcuadorProbabilistic completion analysis using Monte Carlo risk simulation software to test achievability of the remaining programme.
1997 – 1998Daule Peripa hydroelectric plantEcuadorUSD 280 MMBuilt the master baseline schedule for the civil and electromechanical scope and issued monthly updates as consultant.
1997Mica Sur project · PichinchaEcuadorUSD 45 MMInitial planning, schedule updating and cost control.
1996 – 1998Church of Jesus Christ of Latter-day Saints – Guayaquil facilitiesEcuadorUSD 17 MMBaseline development and monthly critical-path progress control.
1995Cigarette plant for Philip Morris, Charlotte NC · Construction Interface Inc.USACost estimation using Timberline, building the reference cost database later used to substantiate claims.
1995Mall del Sol · Conbaquerizo Cía. Ltda.EcuadorUSD 35 MMMaster baseline plan and monthly updates.
1992Marina del Río · Arq. Juan OrúsEcuadorUSD 10 MMProject plan and monthly updates.

Earlier positions

PeriodProject / ClientCountryCapital valueRole and contribution
1990 – 1991Banco del ProgresoEcuadorn/aTechnical support.
1989 – 1990ExcellnetEcuadorn/aTechnical support for PC hardware and Novell NetWare networks.

Planning and project-control training delivered (1992 – 1999)

Client organisations trained in planning, scheduling and cost control: GEP Servicios, Maxus, Coll Construcciones, ConBaquerizo, Procopar, Consultora Vera, ASTEC, Constructora Norberto Odebrecht, CEDEGE, Inmomariuxi C.A., Consorcio Santos CMI and EnCana Ecuador.

Claims and forensic scheduling practice

Claims work is not a recent addition to this practice — it is where it began. Between 1992 and 1999 Martin worked as project consultant for Construction Interface Inc., a US claim-analysis firm, developing its Ecuadorian market and applying its methods on projects in Ecuador and the United States. That period produced two capabilities still in use today: cost-estimating databases built in Timberline for the express purpose of substantiating claims, and probabilistic completion analysis using Monte Carlo simulation to test whether a remaining programme was achievable.

Underpinning credential: AACE International Planning & Scheduling Professional programme, including contract claims and productivity analysis; Past President of the AACE International Ecuador Section and Vice-President of its Peru Section.

Proprietary digital products

Designed, built and put into production between March and August 2026 using AI-assisted development. Published at productos.tecnoadminconsulting.com in six languages.

ProductFunctionality
ConvertidorConverts schedules between Microsoft Project and Primavera P6 in seconds while preserving timephased data: .mpp / .xml → .xer / .pmxml and back. Removes the format barrier between owner, PMC and contractor.
Generador de Paneles
(Dashboard Generator)
Upload a schedule and receive an executive dashboard: S-curve, EAC, Look-Ahead, cost and progress. Accepts MPP, XER, XML and Excel.
Panel de Control
(Control Panel)
Keeps the project dashboard permanently current: the schedule is dropped into a watched folder and the panel republishes itself. Available in six languages (ES, EN, PT, DE, FR, AR). This is the platform behind the Nexa integrated control panel.
Validador DCMA
(DCMA Validator)
Audits a schedule against the DCMA 14-Point Assessment — logic, float, lags, constraints, critical path — returning a quality traffic-light and an instant report. Accepts MPP, XER, XML and PMXML. The same screening used to accept or reject contractor baselines, and to evidence schedule quality in a dispute.
Ponderación diaria
(Daily Weighting)
Turns the schedule and the weekly report into a daily forecast weighted by man-hours: how much progress must be earned each day, week and month through to completion. Breaks man-hours down by discipline against the S-curve.
TecnoAnálisisCompany intelligence for counterparty due diligence: official financial statements, ratios, CIIU sector benchmarking, and AI-assisted SWOT and PESTLE analysis. Used to vet contractors, consultants and partners before award.
Issued LogLive register of issued items by phase, package and discipline: who resolves each one, since when, and what is holding up the works, with a status board.
Formularios de Seguridad
(Safety Forms)
Digital IPERC, PETAR, ATS and site checklists completed from a mobile phone, signed and filed automatically.

Supporting internal platforms

PlatformAccessPurpose
SGPCPsgpcp.tecnoadminconsulting.comProject management and control system: Fastify + React application on PostgreSQL, holding project structure, progress and control data as a single system of record.
Asistenteasistente.tecnoadminconsulting.comAI assistant supporting document review, analysis and query across project information.
APS Viewerviewer.tecnoadminconsulting.comAutodesk Platform Services 3D/BIM model viewer, used to review design models and support 4D construction sequencing.